SPECIAL NOTICES
| # 12-11 Posted 10/06/2011 at 0845 First quarter of 2012, there will be required breaker failure testing which will likely curtail windfarm output at OU WindSpirit, Taloga Wind, Centennial, Keenan and NextEra/Oklahoma Wind Energy Windfarms. |
| # 13-11 Posted 10/06/2011 at 0845 Third quarter of 2012, there will be required terminal testing which will likely curtail windfarm output at OU WindSpirit, Taloga Wind, Centennial, Keenan and NextEra/Oklahoma Wind Energy Windfarms. |
| # 2012-3 Posted 01/26/2012 at 0722 Effective 1000 hours through 1730 hours 2/15/12, there will be required testing that will likely curtail Sooner #2 output to approximately 450 MWs. |
| # 2012-4 Posted 02/02/2012 at 1520 Effective 0800 hours 2/6/12 through 1600 hour 2/24/12, there will be construction outage requiring flowgate control of Redbud total output. |
| # 2012-5 Posted 02/06/2012 at 1443 Effective 0700 hours 2/7/12 through 1700 hours 2/23/12, there will be weekly maintenance outages with possible flowgate curtailments of Sooner #2 generation. |