McClain Project Outages
#1
When: October 18-21
Where:
Intent: Replace 106, 106L2, 106M2
Request: Open 102, 101, 105, 106, 186,
Open & tag 134, 102M2, 101M2, 105M2, 106M2, 186L2
Work phase: Remove breaker and (2) switches. Install new Breaker and (2) switches. OG&E Crew to replace CCVT’s on 138 kV bus #2.
Return: Check open 106, remove tag & close 106L2, 106M2, 186L2, 105M2, 101M2, 102M2, 134, close 106 186,105,101,102
#2
When: October 18-19
Where: Pleasant Valley Substation
Intent: Inspect 183, Replace 183L
Request: Open 183, 184, open & tag 138, 183M, 184M
Work Phase: Remove gas from 183, inspect, return gas to 183, Replace 183L
Return: Remove tag & close 184M, 183L, 183M, and 138
Close 183, 184
#3
When: October 19-20
Where: Pleasant Valley Substation
Intent: Replace 183M
Request: Open 183, 182,
Open & tag 137, 183L, 182L
Work Phase: Replace 183M
Return: Remove tag & close 182L, 183M, 183L, and 137
Close 182, 183
#4
When: October 20-21
Where: McClain Substation
Intent: Inspect 182
Request: Open 182, Open & tag 182L, 182M
Work Phase: Remove gas from 182, inspect, return gas to 182
Return: Remove tag & close 182L, 182 M
#5
When: October 22-23
Where: McClain Substation
Intent: Inspect 183
Request: Open 183, Open & tag 183L, 183M
Work Phase: Remove gas from 183, inspect, return gas to 183
Return: Remove tag & close 183L, 183 M
#6
When: October 21
Where: McClain Substation
Intent: Inspect 184
Request: Open 184, Open & tag 184L, 184M
Work Phase: Remove gas from 184, inspect, return gas to 184
Return: Remove tag & close 184L, 184 M
#7
When: October 24-25
Where: McClain Substation
Intent: Inspect 181
Request: Open 181, Open & tag 181L, 181M
Work Phase: Remove gas from 181, inspect, return gas to 181
Return: Remove tag & close 181L, 181M
#8
When: October 26-27
Where:
Intent: Replace 186, 186L1, 186L2
Request: Open 106,186, 116, Open & tag 134, 131, 106L2, 116L1, 116M1, 106M2
Work Phase: Replace 186, 186L1, 186L2
Return: Remove tag & close 106M2, 116M1, 116L1, 106L2, 131, 134, 186L1, 186L2
Close 116, 106, 186
#9
When: November 9-12
Where: Pleasant Valley Substation
Intent: Replace 181, 181L, 181M
Request: Open 181, 182, 184, open & tag 136, 135, 182L, and 184M
Work Phase: Replace 181, 181L, 181M
Return: Remove tag & close 136, 182L, 184M, 181M, 135, and 181L
Close 181, 182, 184
#10
When: November 13-16
Where: Pleasant Valley Substation
Intent: Replace 182, 182M, 182L
Request: Open 182,183,181, Open & tag 136, 137, 183M, 181M
Work Phase: Replace 182, 182M, 182L
Return: Remove tag & close 181M, 183M, 137, close 182L, 182M, 182
Open 182, close 136, close 182, 181, 183
#11
When: October 29-November 1
Where:
Intent: Replace 116, 116M2, 116L1
Request: Open 112, 111, 115, 116, 186, 131,
Open & tag 112M1, 111M1, 115M1, 116M1, 116L1, and 186L1
Work Phase: Replace 116, 116M2, 116L1, complete work at Sara Road Substation. OG&E work crew replaces CCVT’s on 138 kV bus #1.
Return: Remove tag & close 186L1, 116M1, 116L1, 115M1, 111M1, 112M1
Close 186, 116, open 186, 116, remove tag & close 131, close 186, 116
Close 112, 111, 115,
#12
When: October 29-November 1
Where:
Intent: Replace Switch 133
Request: Open 133, Open & tag T126
Work Phase: Replace Switch 133, complete work at Cimarron Substation
Return: Remove tag & close T126, close 133.
Work
complete at Cimarron Substation for this project.
#13
When: November 2-November 5 May have to split into two outages
Where: Pleasant Valley Substation
Intent: Replace 184, 184L, 184M
Request: Open 184, 181, 183, Open & tag 135, 138, 181L, 183L
Work Phase: Replace 184, 184L, 184M
Return: Remove tag & close 183L, 181L, 184L, 184M, and 138
Close 181, Open 181, Remove tag & close 135
Close 181, 182, 184
Mc
Clain Plant Outage November 8-November 20 starts
#14
When:
November 9-12
Combine with outage #9
Where: McClain Substation
Intent: Replace Switches 181L, 183L
Request: Open 193, 181, 183, Open and tag 131, 193M, 181M, 183M
Work Phase: Replace Switches 181L, 183L (with PASCOR)
Return: Remove tag and close 183M, 181M, 193M, 131, 181L, and 183L
Close 183, 181, and 193
#15
When: November 15-18 Combine with outage #10
Where: McClain Substation
Intent: Replace Switches 182M, 184L
Request: Open 182, 184, Open and tag 132, 182L, 184M,
Work Phase: Replace Switches 182M, 184L (with PASCOR)
Return: Remove tag & close 184M, 182L, 182L, 184L, and 132
Close 184, 182
Plant
Outage November 8-November 20 ends
#16
When: November 30-December 3
Where: McClain Substation Work with outage at Pleasant Valley Substation
Intent: Replace live parts on switches 136, 183M, 182L, replace wave trap
Request: Open 182, 183, Open & tag 182M, 183L
Work Phase: Replace live parts on switches 136, 183M, 182L, replace wave trap
Complete work at Pleasant Valley Substation,
Return: Remove tag & close 183L, 182M, 183M, 182L, and 136
Close 183, 182
#17
When: November 30-December 3
Where: Pleasant Valley Substation Work with outage at McClain Substation
Intent: Replace wave trap and CCVT on McClain Line, switch 138
Request: Open 184, 183, Open & tag 183M and 184M
Work Phase: Replace wave trap and CCVT on McClain Line, switch 138
Complete
work at McClain Substation
Return: Remove tag & close 183M, 184M, and 138
Close 183, 184
Work
at Pleasant Valley Substation complete for this project.
#18
When: December 6- December 9
Where: McClain Substation Work with outage at Sara Road Substation
Intent: Replace wave-trap and live parts on 135, 184M, 181M
Request: Open 181, 184, Open & tag 181L, 184L
Work Phase: Replace wave-trap and live parts on 135, 184M, 181M
Complete work at Sara Road Substation
Return: Remove tag & close 184L, 181L, 135
Close 184, 181
#19
When: December 6- December 9
Where:
Intent: Replace 134
Request: Unload Bank#3, open & tag 123M, T127
Replace: Switch 134, Complete work at McClain Substation,
Return: Close at McClain, close 134, open 134, remove tag & close T127, 123M
Close 134, load bank #3.
Work
at McClain Substation complete for this project.
#20
When: December 10- December 11
Where:
Intent: Replace T126
Request: Unload Bank#2, open & tag 133, T127, 122M,
Replace: T126
Return: Remove tag & close T127, T126, 133,
Close 122M, load bank #2.
#21
When: December 13- December 14 Station Outage
Where:
Intent: Replace T127
Request: Unload Bank#2, Unload Bank#3, open & tag 133, 134, 122M, 123M
Replace: T127
Return: Remove tag & close 133, 134, 122M, 123M,
Load bank #2 and Bank #3.
Work
at Sara Road Substation complete for this project.