McClain Project Outages

 

#1

When:              October 18-21            

Where:             Cimarron Substation    

Intent:               Replace 106, 106L2, 106M2

Request:           Open 102, 101, 105, 106, 186,

Open & tag 134, 102M2, 101M2, 105M2, 106M2, 186L2

Work phase:     Remove breaker and (2) switches.  Install new Breaker and (2) switches.  OG&E Crew to replace CCVT’s on 138 kV bus #2.

Return:             Check open 106, remove tag & close 106L2, 106M2, 186L2, 105M2, 101M2, 102M2, 134, close 106 186,105,101,102

 

#2

When:              October 18-19

Where:             Pleasant Valley Substation

Intent:               Inspect 183, Replace 183L

Request:           Open 183, 184, open & tag 138, 183M, 184M

Work Phase:    Remove gas from 183, inspect, return gas to 183, Replace 183L

Return:             Remove tag & close 184M, 183L, 183M, and 138

                        Close 183, 184

 

#3

When:              October 19-20

Where:             Pleasant Valley Substation

Intent:               Replace 183M

Request:           Open 183, 182,

Open & tag 137, 183L, 182L

Work Phase:    Replace 183M

Return:             Remove tag & close 182L, 183M, 183L, and 137

                        Close 182, 183

 

#4

When:              October 20-21

Where:             McClain Substation

Intent:               Inspect 182

Request:           Open 182, Open & tag 182L, 182M

Work Phase:    Remove gas from 182, inspect, return gas to 182

Return:             Remove tag & close 182L, 182 M

 

#5

When:              October 22-23

Where:             McClain Substation

Intent:               Inspect 183

Request:           Open 183, Open & tag 183L, 183M

Work Phase:    Remove gas from 183, inspect, return gas to 183

Return:             Remove tag & close 183L, 183 M

 

#6

When:              October 21

Where:             McClain Substation

Intent:               Inspect 184

Request:           Open 184, Open & tag 184L, 184M

Work Phase:    Remove gas from 184, inspect, return gas to 184

Return:             Remove tag & close 184L, 184 M

 

#7

When:              October 24-25

Where:             McClain Substation

Intent:               Inspect 181

Request:           Open 181, Open & tag 181L, 181M

Work Phase:    Remove gas from 181, inspect, return gas to 181

Return:             Remove tag & close 181L, 181M

 

#8

When:              October 26-27

Where:             Cimarron Substation

Intent:               Replace 186, 186L1, 186L2

Request:           Open 106,186, 116, Open & tag 134, 131, 106L2, 116L1, 116M1, 106M2

Work Phase:    Replace 186, 186L1, 186L2

Return:             Remove tag & close 106M2, 116M1, 116L1, 106L2, 131, 134, 186L1, 186L2

                        Close 116, 106, 186

 

#9

When:              November 9-12          

Where:             Pleasant Valley Substation

Intent:               Replace 181, 181L, 181M

Request:           Open 181, 182, 184, open & tag 136, 135, 182L, and 184M

Work Phase:    Replace 181, 181L, 181M

Return:             Remove tag & close 136, 182L, 184M, 181M, 135, and 181L

                        Close 181, 182, 184

 

#10

When:              November 13-16

Where:             Pleasant Valley Substation

Intent:               Replace 182, 182M, 182L

Request:           Open 182,183,181, Open & tag 136, 137, 183M, 181M

Work Phase:    Replace 182, 182M, 182L

Return:             Remove tag & close 181M, 183M, 137, close 182L, 182M, 182

                        Open 182, close 136, close 182, 181, 183

   

#11

When:              October 29-November 1

Where:             Cimarron Substation, work with outage at Sara Road Substation.

Intent:               Replace 116, 116M2, 116L1

Request:           Open 112, 111, 115, 116, 186, 131,

                        Open & tag 112M1, 111M1, 115M1, 116M1, 116L1, and 186L1

Work Phase:    Replace 116, 116M2, 116L1, complete work at Sara Road Substation.  OG&E work crew replaces CCVT’s on 138 kV bus #1.

Return:             Remove tag & close 186L1, 116M1, 116L1, 115M1, 111M1, 112M1

                        Close 186, 116, open 186, 116, remove tag & close 131, close 186, 116

                        Close 112, 111, 115,

 

#12

When:              October 29-November 1  

Where:             Sara Road Substation, work with outage at Cimarron Substation.

Intent:               Replace Switch 133

Request:           Open 133, Open & tag T126

Work Phase:    Replace Switch 133, complete work at Cimarron Substation

Return:             Remove tag & close T126, close 133.

 

Work complete at Cimarron Substation for this project.

#13

When:              November 2-November 5        May have to split into two outages

Where:             Pleasant Valley Substation

Intent:               Replace 184, 184L, 184M

Request:           Open 184, 181, 183, Open & tag 135, 138, 181L, 183L

Work Phase:    Replace 184, 184L, 184M

Return:             Remove tag & close 183L, 181L, 184L, 184M, and 138

                        Close 181, Open 181, Remove tag & close 135

                        Close 181, 182, 184

 

Mc Clain Plant Outage November 8-November 20 starts

 

#14

When:              November 9-12           Combine with outage #9

Where:             McClain Substation

Intent:               Replace Switches 181L, 183L

Request:           Open 193, 181, 183, Open and tag 131, 193M, 181M, 183M

Work Phase:    Replace Switches 181L, 183L (with PASCOR)

Return:             Remove tag and close 183M, 181M, 193M, 131, 181L, and 183L

                        Close 183, 181, and 193

#15

When:              November 15-18         Combine with outage #10

Where:             McClain Substation

Intent:               Replace Switches 182M, 184L

Request:           Open 182, 184, Open and tag 132, 182L, 184M,

Work Phase:    Replace Switches 182M, 184L (with PASCOR)

Return:             Remove tag & close 184M, 182L, 182L, 184L, and 132

                        Close 184, 182

 

Plant Outage November 8-November 20 ends

 

#16

When:              November 30-December 3

Where:             McClain Substation      Work with outage at Pleasant Valley Substation

Intent:               Replace live parts on switches 136, 183M, 182L, replace wave trap

Request:           Open 182, 183, Open & tag 182M, 183L

Work Phase:    Replace live parts on switches 136, 183M, 182L, replace wave trap

                        Complete work at Pleasant Valley Substation,

Return:             Remove tag & close 183L, 182M, 183M, 182L, and 136

                        Close 183, 182

 

#17

When:              November 30-December 3

Where:             Pleasant Valley Substation     Work with outage at McClain Substation

Intent:               Replace wave trap and CCVT on McClain Line, switch 138

Request:           Open 184, 183, Open & tag 183M and 184M

Work Phase:    Replace wave trap and CCVT on McClain Line, switch 138

Complete work at McClain Substation

Return:             Remove tag & close 183M, 184M, and 138

Close 183, 184

 

Work at Pleasant Valley Substation complete for this project.

 

#18

When:              December 6- December 9

Where:             McClain Substation      Work with outage at Sara Road Substation

Intent:               Replace wave-trap and live parts on 135, 184M, 181M

Request:           Open 181, 184, Open & tag 181L, 184L

Work Phase:    Replace wave-trap and live parts on 135, 184M, 181M

                        Complete work at Sara Road Substation

Return:             Remove tag & close 184L, 181L, 135

                        Close 184, 181

 

#19

When:              December 6- December 9

Where:             Sara Road Substation   Work with outage at Mc Clain Substation

Intent:               Replace 134

Request:           Unload Bank#3, open & tag 123M, T127

Replace:           Switch 134, Complete work at McClain Substation,

Return:             Close at McClain, close 134, open 134, remove tag & close T127, 123M

                        Close 134, load bank #3.

 

Work at McClain Substation complete for this project.

 

#20

When:              December 10- December 11

Where:             Sara Road Substation

Intent:               Replace T126

Request:           Unload Bank#2, open & tag 133, T127, 122M,

Replace:           T126

Return:             Remove tag & close T127, T126, 133,

                        Close 122M, load bank #2.

#21

When:              December 13- December 14      Station Outage

Where:             Sara Road Substation

Intent:               Replace T127

Request:           Unload Bank#2, Unload Bank#3, open & tag 133, 134, 122M, 123M

Replace:           T127

Return:             Remove tag & close 133, 134, 122M, 123M,

                        Load bank #2 and Bank #3.

 

Work at Sara Road Substation complete for this project.